Single Window Clearance
 
 
 
Single Window Clearance and Clearance from different bodies like PCB, PSEB

A System to provide single window service to the entrepreneurs has been launched by he State Government. The State Govt. under this system, had devised a Single Composite Application Form for Clearance relating to release of Power Connection by P.S.E.B, Grant of NOC/Consent to operate under Water & Air Pollution Control Act by PPCP and Site Approval under the Factories Act, 1948 by the Factories Department. The Clearances will be granted in fixed time schedule for setting up Industrial Units in the Punjab.

The Govt. has constituted an Empowered Committee with the following composition:-
 

1. Composition
  Chief Secretary Chairman
  1.          Principal Secretary to Chief Minister

2.          Principal Secretary, Industries & Commerce

3.          Principal Secretary, Irrigation and Power

4.          Secretary, Environment

5.          Secretary, Housing & Urban Development

6.          Secretary, Labour

7.          Director of Industries, Punjab

 
Convenor.
  The Chairman of Committee may co-opt other Administrative Secretaries/ State Government Officials, as and when required.

2.

Powers and Functions
  The powers and functions of the Empowered Committee shall be as under:-
1.           To monitor sanction/clearances from the environmental, locational and other aspects to entrepreneurs setting up large and medium industries.

2.         To oversee the implementation of Industrial Policy 1996, by the Department/Agencies concerned in the State Government.
3. Procedures
1.        The Empowered Committee shall lay down its own procedure for the transaction of business and the decisions taken             by it shall be implemented by Government/ Agencies in the interest of promotion and growth of industry in the State.

2.        The entrepreneurs shall give information regarding inputs/clearances needed for the project in the Composite             Application Form to Udyog Sahayak.

3.        Udyog sahayak shall transmit composite applications received from entrepreneurs to the Department/Agency            concerned for getting their approval/ clearances within the time frame indicated in the Appendix

4.        These cases after due processing would be put up to the empowered committee.

5.        The approval/clearance granted by the Empowered Committee shall be valid for two years. It shall be extended for            one year in genuine cases where delay had occurred due to the circumstances beyond the control of the entrepreneurs.

6.        The Empower Committee shall meet once in a month or earlier, if necessary.

 

4. Executive Committee An Executive Committee with the following composition is hereby constituted to assist the Empowered Committee by monitoring the disposal of applications that are sent to the various Departments/Agencies for approval/Clearance:-
  Director of Industries, Punjab Chairman
  Dy Chairman and Managing Director,  Punjab State Industrial Development Corporation Limited. Member
  Managing Director, Punjab Small Industries and Export Corporation Member
  Managing Director, Punjab Financial Corporation Member
  Managing Director, Punjab State Electronics Development and Production Corporation Ltd. Member
  Chief Engineer Commercial, Punjab State Electricity Board, Patiala Member
  Chief Town Planner, Punjab Member
  Member Secretary, Pollution Control Board, Patiala Member
  Industrial Adviser-cum-Additional Director, Industries, Punjab Member
  Chief Coordinator, Udyog Sahayak Member Secretary
  Chief Conservator for Forests Member
  Chief General Manager Telecom Member
Besides, the Executive Committee shall also be competent to sanction expenditure, approve appointment to Udyog Sahayak and exercise administrative control over its staff. The executive Committee shall meet once in a month. Executive Committee would also deliberate, once in two month, issues pertaining to the existing industrial units. Representatives of concerned departments would be requested to attend such meetings as special invitees.
5. The Administrative Department of State Government shall immediately issue necessary directions/instructions to the Head of Department/Agencies under their administrative control so that they assign top priority to the cases being sent by Udyog Sahayak under Single Window Clearance Scheme and immediately implement the orders of the Empowered Committee. The constitution of Empowered Committee and Executive Committee and their functions shall be changeable at any time and with the approval of Chief Minister
6. Single Window Committee at District Level:
A Single Window Committee will function at District level with following composition:-

 

Deputy Commissioner

Chairman

  1        Environmental Engineer, Punjab Pollution Control Board,

2.       Superintending Engineer/Executive Engineer of PSEB,

3.       District Officer of Housing and Urban Development, Authority

4.       Assistant Director of Factories
  General Manager, District Industries Centre, Convenor
  The above committee will provide sanctions/clearance for setting up of small scale Industrial Units in the state. The Committee will meet once in a month or earlier, if necessary.

Annexure

Sr. No.
Department
Service/Facility
Time Limit
1.
Department of Industries, Govt. Punjab
i. Sponsoring of Composite applications to the concerned     Department/Agency
5 days
ii. Recommendation to GOI for Letter of Intent/ Industrial     License     and Registration for Milk Products.
2 Weeks
iii. Sponsorship for essential Raw Material/ inputs
4 Weeks
iv. Allotment of plots in Industrial focal points/Growth     Centres out of "Off the Shelf" Quota
4 Weeks
v. Incentives
 
a.
Investment Incentive
4 Weeks
b.
Sales Tax exemption
1 Weeks
c.
Any other incentive
2 Weeks


 
vi. Sanction of Loan by PFC/PSIDC
8 Weeks
vii. Registration of Boiler by Chief Inspector of Boiler.
3 Weeks after the receipt of application if requirements are satisfied.
2.
Department of Environment
i. Site approval/ environmental clearance by CSA for 20     highly polluting Industries 2 months after the receipt of application
ii. Adequacy Certificate by the Competent State Authority     (CSA) 1 month from the receipt of application
iii. NOC from Pollution Control Board in respect of
 
Green Category
a.
Marginally Polluting Industries 15 days from the receipt of application
b.
Moderately Polluting Industries 1 month from the receipt of application
Red Category
a.
Clearance Certificate from Pollution Control Board.
One Month from the date of receipt of application
b.
Sanction to operate from Pollution Control Board in respect of:
1 Month after submission of compliance of NOC.
c.
Renewal of Consent from the Pollution Control Board.
3 months after submission of application with 2 months of submission of renewal request.
 


 

3.
Chief Inspector of Factories
i. Site Clearance for 29 hazardous industries from the point of     view of health, safety and welfare of the workers.
2 months from the date of receipt of complete applications
ii. Approval of Factory Plan under Factories Act, 1948.
Within 1 month from the date of submission of application.
iii. License for running the factory to be issued by the field     Officer
2 weeks after receipt of application
4.
P.S.E.B
Sanction of Power:
S.P. (upto 20 K.W)
a.
Issue of Demand Notice
4 Weeks
b.
Release of connection after compliance of demand Notice
8 Weeks
M.S. (21-99 KW)
a.
Issue of demand Notice
4 Weeks
b.
Release of Connection
12 Weeks
L.S (Upto 500 KW)
 
Issue of demand Notice
60 Days
 
Release of Connection
12 Weeks
L.S. (above 500 KW)
a.
Feasibility study
90 Days
b.
Issue of Demand Notice
60 Days
c.
Release of connection 11 KV
90 Days

 

 

These Documents are available in PDF format. Please use Acrobat Reader.
(available for free download at )

All Rights Reserved with Department of Industries, Punjab, India
WebSite developed by : Technorite Consultants Pvt. Ltd.