| 1. |
Composition |
| |
Chief
Secretary |
Chairman |
| |
1. Principal Secretary to Chief Minister
2. Principal Secretary, Industries & Commerce
3. Principal Secretary, Irrigation and Power
4. Secretary, Environment
5. Secretary, Housing & Urban Development
6. Secretary, Labour
7. Director of Industries, Punjab
|
Convenor. |
| |
The
Chairman of Committee may co-opt other Administrative
Secretaries/ State Government Officials, as and when
required. |
2. |
Powers and Functions |
| |
The
powers and functions of the Empowered Committee shall be
as under:-
1. To monitor sanction/clearances from the
environmental, locational and other aspects to
entrepreneurs setting up large and medium industries.
2. To oversee the implementation of Industrial
Policy 1996, by the Department/Agencies concerned in the
State Government. |
| 3. |
Procedures
1. The Empowered Committee shall lay down its own
procedure for the transaction of business and the
decisions taken by it shall be implemented
by Government/ Agencies in the interest of promotion and
growth of industry in the State.
2. The entrepreneurs shall give information
regarding inputs/clearances needed for the project in
the Composite Application Form to Udyog
Sahayak.
3. Udyog sahayak shall transmit composite
applications received from entrepreneurs to the
Department/Agency concerned for getting their
approval/ clearances within the time frame indicated in
the Appendix
4. These cases after due processing would be put
up to the empowered committee.
5. The approval/clearance granted by the
Empowered Committee shall be valid for two years. It
shall be extended for one year in genuine
cases where delay had occurred due to the circumstances
beyond the control of the entrepreneurs.
6. The Empower Committee shall meet once in a
month or earlier, if necessary.
|
| 4. |
Executive Committee An Executive
Committee with the following composition is hereby
constituted to assist the Empowered Committee by
monitoring the disposal of applications that are sent to
the various Departments/Agencies for
approval/Clearance:- |
| |
Director of Industries, Punjab |
Chairman |
| |
Dy
Chairman and Managing Director, Punjab State Industrial
Development Corporation Limited. |
Member |
| |
Managing Director, Punjab Small Industries and Export
Corporation |
Member |
| |
Managing Director, Punjab Financial Corporation |
Member |
| |
Managing Director, Punjab State Electronics Development
and Production Corporation Ltd. |
Member |
| |
Chief
Engineer Commercial, Punjab State Electricity Board,
Patiala |
Member |
| |
Chief
Town Planner, Punjab |
Member |
| |
Member Secretary, Pollution Control Board, Patiala |
Member |
| |
Industrial Adviser-cum-Additional Director, Industries,
Punjab |
Member |
| |
Chief
Coordinator, Udyog Sahayak |
Member Secretary |
| |
Chief
Conservator for Forests |
Member |
| |
Chief
General Manager Telecom |
Member |
| Besides, the Executive Committee shall also be competent
to sanction expenditure, approve appointment to Udyog
Sahayak and exercise administrative control over its
staff. The executive Committee shall meet once in a
month. Executive Committee would also deliberate, once
in two month, issues pertaining to the existing
industrial units. Representatives of concerned
departments would be requested to attend such meetings
as special invitees. |
| 5. |
The
Administrative Department of State Government shall
immediately issue necessary directions/instructions to
the Head of Department/Agencies under their
administrative control so that they assign top priority
to the cases being sent by Udyog Sahayak under Single
Window Clearance Scheme and immediately implement the
orders of the Empowered Committee. The constitution of
Empowered Committee and Executive Committee and their
functions shall be changeable at any time and with the
approval of Chief Minister |
| 6. |
Single Window Committee at
District Level:
A Single Window Committee will function at District
level with following composition:- |
|
Deputy Commissioner |
Chairman |
| |
1
Environmental Engineer, Punjab Pollution Control
Board,
2. Superintending Engineer/Executive Engineer of
PSEB,
3. District Officer of Housing and Urban
Development, Authority
4. Assistant Director of Factories |
| |
General Manager, District Industries Centre, |
Convenor |
| |
The
above committee will provide sanctions/clearance for
setting up of small scale Industrial Units in the state.
The Committee will meet once in a month or earlier, if
necessary. |
Sr.
No. |
Department |
Service/Facility |
Time
Limit |
1. |
Department of Industries, Govt. Punjab |
i. Sponsoring of Composite
applications to the concerned Department/Agency |
5
days |
| ii. Recommendation to GOI
for Letter of Intent/ Industrial License and
Registration for Milk Products. |
2
Weeks |
| iii. Sponsorship for
essential Raw Material/ inputs |
4
Weeks |
| iv. Allotment of plots in
Industrial focal points/Growth Centres out of "Off
the Shelf" Quota |
4
Weeks |
v.
Incentives
a. |
Investment
Incentive |
4 Weeks |
b. |
Sales Tax exemption |
1 Weeks |
c. |
Any other incentive |
2 Weeks |
|
|
| vi. Sanction of Loan by PFC/PSIDC |
8
Weeks |
| vii. Registration of Boiler
by Chief Inspector of Boiler. |
3
Weeks after the receipt of application if requirements
are satisfied. |
2. |
Department of Environment |
i. Site approval/
environmental clearance by CSA for 20 highly
polluting Industries |
2 months after the receipt
of application |
| ii. Adequacy Certificate by
the Competent State Authority (CSA) |
1 month from the receipt of
application |
iii. NOC from Pollution
Control Board in respect of
Green Category |
a. |
Marginally Polluting
Industries |
15 days from the
receipt of application |
b. |
Moderately Polluting
Industries |
1 month from the
receipt of application |
Red Category |
a. |
Clearance Certificate
from Pollution Control Board. |
One Month from the
date of receipt of application |
b. |
Sanction to operate
from Pollution Control Board in respect of: |
1 Month after
submission of compliance of NOC. |
c. |
Renewal of Consent
from the Pollution Control Board. |
3 months after
submission of application with 2 months of
submission of renewal request.
|
|
3. |
Chief Inspector of Factories |
i. Site Clearance for 29
hazardous industries from the point of view of
health, safety and welfare of the workers. |
2
months from the date of receipt of complete
applications |
| ii. Approval of Factory
Plan under Factories Act, 1948. |
Within 1 month from the date of submission of
application. |
| iii. License for running
the factory to be issued by the field Officer |
2
weeks after receipt of application |
4. |
P.S.E.B |
Sanction of Power:
S.P. (upto 20 K.W) |
a. |
Issue of Demand
Notice |
4 Weeks |
b. |
Release of connection
after compliance of demand Notice |
8 Weeks |
M.S. (21-99 KW) |
a. |
Issue of demand
Notice |
4 Weeks |
b. |
Release of Connection |
12 Weeks |
L.S (Upto 500 KW) |
|
Issue of demand
Notice |
60 Days |
|
Release of Connection |
12 Weeks |
L.S. (above 500 KW) |
a. |
Feasibility study |
90 Days |
b. |
Issue of Demand
Notice |
60 Days |
c. |
Release of connection
11 KV |
90 Days |
|